Mackay Conservation Group joins Eastpoint Mackay matters in P & E Court

04 May, 2012

Mackay Conservation Group Inc (MCG) was successful in its application to the Planning and Environment Court for an order that it be included as a party in matters brought by developer Eastpoint Mackay Pty Ltd. 

The developer sought to extend the time limit for the building of the hotel component of a major development on a coastal site at Eastpoint, Mackay. That development was approved in 2004 despite an appeal by MCG.

His Honour Judge Robertson recognised that MCG’s interest in the matters is in the public interest and concluded that MCG is an entity whose presence before the Court would be desirable, just and convenient to enable the Court to determine effectively and completely the issue raised in Eastpoint’s application and appeal.

EDO Qld represented MCG in their successful application and will continue to represent MCG in both matters. 

Thank you to barrister Mr James Dillon for his advocacy work on this matter.

Environmental Defenders Office Queensland (EDO Qld) gives a strong legal voice to the environment when needed most.

Take Action

The latest from EDO Qld

EVENT: What Judges Want 2019

We are on Adani’s secret hit list – help us fight back

Factsheet: Community Rights and the Water Act 2000 (Qld)

Vale Dr John Sinclair AO

Eyes in the sky: Drones and environmental monitoring